M-19 Railroad Crossing Reconstruction
 

Monday, July 12, 2004 – Friday, July 30, 2004

The Michigan Department of Transportation (MDOT) and Canadian National Railway (CN) will be reconstructing the railroad crossing of Main Street (M-19) during the last three weeks of July. These repairs are necessary due to the increasingly poor condition of the crossing, which is causing traffic problems. These repairs will include a total reconstruct of the crossing that will take 19 days to complete. The crossing will be shut down to vehicular traffic from July 12th through July 30th. CN will complete the railroad portion of the crossing and MDOT will repave the approaches on M-19.

The tentative time-line is 19 days
July 12th – July 21st Railroad crossing work
July 21st – July 30th MDOT work


Businesses along Main Street between Division Road and Gratiot Avenue will remain accessible by local traffic. Once in the Granary District residents and customers can utilize Howard Street to Division Road and Gleason Avenue to Forest Avenue to get around the crossing. Howard Street, Gleason Avenue, Beech Street, and Oak Street will remain open to traffic. Please support our local merchants.

Thanks for visiting!
Jim Hanus

www.AllAboutRichmond.com
email: list@allaboutrichmond.com

 
     

[All About Richmond Homepage] [Business Directory] [Local Events]
All About Richmond is sponsored and maintained by Jim Hanus and Michigan Imaging Supply L.L.C.
 Copyright 2000-2007 MIS L.L.C. All rights reserved.
Not affiliated with the City of Richmond, Michigan. No commercial reproduction, adaptation,
distribution or transmission of any part or parts of this website or any information contained therein
 by any means whatsoever is permitted without the prior written permission of MIS.
Questions or Comments? Send us Email. Website Design by MIS LLC - Specifications subject to change.
Please read our Disclaimer and Service Agreement. - Last updated 02/20/2008 06:51:52 AM.